General:
NB001 inside hull sealing and undercoating commenced. The temperature in the shed has still been cold this week and this has had an effect on the time taken for the sealer and paint to dry.
The keel for NB002 is being worked on in the workshop.
Details:
NB001 inside hull is now sealed and the first undercoat has been applied. The filling of bumps and dents of the inside planking is now underway before the top coats can be applied this week.
The seats are now in the process of being cut.
NB002 awaits the arrival of it’s keel in the shed before installation on the boat.
[flickr photo=14302118731 size=medium]