Build Progress Week 31

NB001

 

Top Cover now in North Berwick but a ridge pole and frames required to be fabricated before this can be fitted on the boat.

  

NB002

The outside of the hull is now faired and ready for the painting process to commence.  Note: the fairing has taken two or three days longer than expected but we are still pushing for completion in 2 weeks.

 

Work Targets for Wk 32.

 

NB001: Ridge pole and frames to be made thus allowing the fitting of the boats cover.

  

NB002: Painting process to commence.  Note: 2 coats of sealer, 2 coats of undercoat before 2 coats to top coat.