NB1 will officially be given her name on 7th July at 20:30, at an informal ceremony to be held on the West Beach close to the lifeboat slip, to which all are cordially invited.  Work of our artist in residence, Georgina Bown, which follows the progress of the build, will be exhibited at Greens and Blues …

Portsoy

Well done to everyone who rowed, coxed or supported at Portsoy. Particular congratulations to the winners of the Over 40’s Mixed Crew, who are probably all feeling thier age today. What a fantastic weekend!

Port Seton

Well done to all of those who rowed at Port Seton on Saturday. Once again our fabulous ladies crew showed the rest of us how it should be done.  However no one was left behind by too much, and we are all learning fast. 

Build Progress Wk18

NB001 has now had it’s hull faired and sanded. The outside hull will start to be painted this week. The manufacture of seats and beams has now been completed which will allow sanding and varnishing to commence. NB002 has had it’s keel fitted and is currently lying in Bay B. The clean-up of the inside …

Build Progress Wk17

NB001 inside hull now painted. Ready for turnover for painting of outside of hull. The hull is now ready to placed back on the building frame to have it’s outside faired, sealed and painted.  The manufacture of seats and beams are progressing well and should be ready for varnishing next week..  The keel for NB02 …

Boat Name

After looking through hundreds of suggestions from the pupils of Law Primary and whittling them down to a shortlist of six, North Berwick’s community boat builders and future representatives of the town in rowing races against their neighbours have chosen the name “St Baldred” to be given to their first “St Ayles skiff”, a four …

Build Progress Wk16

General: NB001 inside hull sealing and undercoating commenced.  The temperature in the shed has still been cold this week and this has had an effect on the time taken for the sealer and paint to dry. The keel for NB002 is being worked on in the workshop.  Details: NB001 inside hull is now sealed and the first undercoat …

Build Progress Wk15

General: Progress has been made on NB01 with the inside hull now sanded and ready for the painting process to commence. The keel for NB02 is being manufactured in the workshop Details: NB001 inside hull is now sanded and ready for the painting process to commence. The first batch of sealer and undercoat has arrived and a coat was …

Build Progress Wk13/Wk14

NB001 top inner rail is now completed installed. Frame tops installed and templates being made to allow the manufacture of the beams and thwarts (seats). Note this work will not prevent the painting of the inside hulll when sanding is complete. NB002 planking has gone to schedule this week and is now 100% complete. [flickr photo=14302190271 …